viewed: 日期:2014/3/20 15:58:36
In December, 2013, Boqi Company signed Shenhua Guohua Shouguang Power Plant Phase I Flue Gas Desulfurization Project Contract with Shenhua Guohua Shouguang Electric Company Ltd. This project is EPC general contracting project and adopting our independent developed technology, wet limestone-gypsum spray tower. It is required that the desulfurization efficiency should not less than 98% and concentration in the exit should not higher than 50 mg/Nm3. Shenhua Guohua Shouguang Power Plant has 2*1000MW ultra supercritical generating units. This project is the 8th million level project of Boqi Company. Until to now, Boqi Company has 15 contracts in million level.
The project goes smoothly at present. It is predicted that the project will be put into operation in April, 2016. And 46,000 ton SO2 will be reduced to emit.