viewed: 日期:2015/7/1 11:04:03
In the beginning of April, 2015, the EPC project department started the spring safety and quality inspection. The inspection strictly followed the requirements of Notice of 2015 Spring Safety and Quality Inspection. It established a good basis for safe and standard construction work by scrutiny, taking preventive measures, promoting and implementing the state’s Safety Production Law.
This inspection lasted 43 days, took 13374 kilometers long, inspected 7 EPC projects and found out in total 262 safety and quality hidden dangers in various kinds. According to the actual situation of each projects, the inspection team checked the management, sites, materials and trainings. The problems checked out was presented by PPT form and given detailed explanation, analysis and comments. The following preventive measure also guided by the team. There were 374 persons accepted the safety and quality training in this inspection. The training promoted the employees self-prevention consciousness and formed a safe construction atmosphere in mutual supervision and reminding. The management in all levels, based on the principle of “people oriented”, took special treatment for the safe production environment.
The spring inspection was supported by each projects department. It achieved good results on safety and quality hidden dangers rectification. In the future work, we should observe the ides of “Macro-Security” and establish a solid safety basis for creating excellent works.