Although the short construction period and difficulty conditions, Shandong Nanshan Yili #3 unit passed the 168 hours trial operation on December 6th, 2016 with the joint efforts of all staff and the great supports from the leaders. It was 2 days ahead of schedule. The #2 unit passed the 168 hours trial operation test on February 13th, 2016, which was 26 days ahead of schedule. When the #2 unit started, it happened to extremely cold. The lowest air temperature in shangdong was 17 degree below zero, on which condition it was frozen in the room. Our project department and construction company overcame a lot of difficulties and made great efforts to ensure the system normal operation and completion ahead of schedule.