viewed: 日期:2016/4/27 15:28:21
Shanxi Yongji Cogeneration 2*350 MW Desulfurization BOT Project, contracted to build by our company, is the first ultra low emission power plant in Shanxi Province. With the attention from company leaders and great supports of all departments, the project staff completed the 168 trial full load operation for #3 and #4 desulfurization systems on December 31st, 2015 and March 28th, 2016 separately. All the indexes meet the designing requirements and ultra low standards. The desulfurization project won the praise from the owners.
It was accomplished by high responsibility, standard management, safe and high quality, the joint efforts of the project staff.